Insights Legal & Finance
Is buying off-plan in Dubai safe? How escrow protects you
Regulated rather than guaranteed. Every payment goes into an escrow account at a DLD-approved bank, ring-fenced and released on the Land Department's terms.
Sandor Domokos 8 min read
Regulated rather than guaranteed: the law protects your money, not the timetable or the price. Since 2007 every dirham an off-plan buyer pays must go into an escrow account in the project's name at a bank approved by the Dubai Land Department, ring-fenced from the developer's creditors and spent only on that project (Government of Dubai, Law 8 of 2007). If RERA cancels the project, the developer must refund all payments (Government of Dubai, Law 19 of 2017).
Key facts
- Retention: 5 per cent of each account is held back at the completion certificate and released a year after the units are registered (Government of Dubai, Law 8 of 2007).
- Release: only on the Land Department's activation terms, against a Department technical report under three months old (Dubai Land Department, Escrow Account activation, 3 Sep 2026).
- Entry price for a developer: a 30 per cent guarantee and a fee of AED 150,000 plus AED 20 (Dubai Land Department, Register Project, 3 Sep 2026).
What is an escrow account, and what does Law 8 of 2007 require?
An escrow account is the bank account of a single development into which every payment by an off-plan purchaser or project lender is deposited (Government of Dubai, Law 8 of 2007). The bank must be one of the Land Department's approved trustees, 29 institutions on 8 September 2026 (Dubai Land Department, Approved escrow account trustees, 3 Sep 2026).
Three provisions do the protecting. The account is opened in the name of the project, under an agreement lodged with the Land Department. It is dedicated exclusively to that project's construction, and no attachment may be placed on the deposits for the benefit of the developer's creditors. And the bank must send the Department regular statements, which it may audit at any time (Government of Dubai, Law 8 of 2007, Arts 7, 9 and 11).
How does money leave the account?
On terms the Land Department sets, not the developer. Before anything is disbursed the account must be activated, which requires the project payment plan, compliance with the Department's financial risk standards, and a Department technical report under three months old with no red flags (Dubai Land Department, Escrow Account activation, 3 Sep 2026).
Release then follows how the project was secured: under a bank guarantee, construction works up to 20 per cent completion, to the value of the guarantee; where the developer or its bank deposited funds, no more than was deposited; under the solvency route, a percentage of the works after 20 per cent completion, on a recent Department technical report (Dubai Land Department, Escrow Account activation, 3 Sep 2026). Law 8 of 2007 creates the account; the Department's activation terms govern what leaves it.
Once the completion certificate is issued, the bank retains 5 per cent of the account and releases it one year after the units are registered in the purchasers' names (Government of Dubai, Law 8 of 2007, Art. 14).
What must a developer do before it can sell?
No developer may operate unless entered in the Land Department's register and licensed, or advertise off-plan without written authorisation (Government of Dubai, Law 8 of 2007, Arts 4 and 5). A sale made before the authorities approve commencement is void (Government of Dubai, Resolution 6 of 2010, Art. 11).
Registering the project is the step that opens the escrow account. The Land Department's current published requirements are an ownership deed, since preliminary sales certificates are not accepted; registration in Trakheesi; approved plans; and a 30 per cent guarantee, met by completing 30 per cent of construction, a bank guarantee covering 30 per cent, or a 30 per cent cash deposit. The fee is AED 150,000 plus AED 20 (Dubai Land Department, Register Project, 3 Sep 2026).
Two thresholds, two purposes: the 30 per cent guarantee is a condition of registering the project; the 20 per cent completion mark belongs to the activation terms described above.
What happens if a project stalls or is cancelled?
Where a project is not completed, the escrow agent must, after consulting the Land Department, act to preserve depositors' rights and ensure the project is completed or depositors refunded (Government of Dubai, Law 8 of 2007, Art. 15). Where RERA cancels a project by reasoned decision, the developer must refund all payments made by purchasers under the procedures of Law 8 of 2007 (Government of Dubai, Law 19 of 2017, Art. 11).
Disputes go to the Special Tribunal for Unfinished and Cancelled Real Property Projects, created by Decree 33 of 2020. It may order the escrow agent or the developer to refund amounts deposited in the escrow account or paid to the developer, and its awards are not open to ordinary appeal (Government of Dubai, Decree 33 of 2020, Arts 7 and 11).
What does escrow not protect against?
Delay, quality and value. We find nothing in Law 8 of 2007, Law 13 of 2008 as amended, or Decree 33 of 2020 that gives a buyer a remedy for late delivery, finish quality or a fall in market value. Escrow protects the money paid, not the timetable or the outcome; remedies for delay are those in the sale and purchase agreement. The one quality-adjacent rule is that a delivered net area more than 5 per cent smaller than agreed must be compensated (Government of Dubai, Resolution 6 of 2010, Art. 13).
Hence the trusted portals' advice: confirm registration, match the escrow account on the contract to the project, never pay a third-party account, and check that payment milestones follow construction rather than the calendar (Betterhomes, 25 Aug 2026; Property Finder, 2 Sep 2026).
Seven checks before you pay a deposit
All are free, on dubailand.gov.ae or in Dubai REST.
| Check | What you are confirming | Where |
|---|---|---|
| 1. Developer licence | The developer is on the Land Department's list | Licensed Developers |
| 2. Project registration | The project has a number, status and start date | Project Status Enquiry |
| 3. Escrow bank and account | SPA bank and account match those shown for the project, at an approved trustee | Project Status Enquiry; Approved escrow account trustees |
| 4. Completion and inspection | Completion percentage and last inspection fit the payment plan | Project Status Enquiry, Dubai REST, or WhatsApp 8004488 |
| 5. Trakheesi permit | Advert carries a valid permit and Madmoun QR code, mandatory since 24 April 2023 | Verify License and Permits; scan the QR |
| 6. Broker licence | The agent's broker number is on RERA's list | Licensed Real Estate Brokers |
| 7. Oqood, after purchase | Your sale is entered in the interim register within 90 days of signing | Developer registers it through Oqood; ask for the certificate |
Sources: Dubai Land Department, the service pages named in the Where column, all updated 3 Sep 2026; Dubai Land Department, 18 Apr 2023.
Our view
In our experience the escrow system does what it was designed to do: it separates the buyer's money from the developer's balance sheet. The failures we see are rarely failures of the law. They are payments made to an account that was not the project's, deposits handed over at exhibitions, where only preliminary reservations are permitted (Dubai Land Department, Real Estate Ad Permit, 3 Sep 2026), and contracts signed before anyone looked up the project number.
We advise treating the seven checks as a condition of the deposit, not a formality after it. Set the payment plan against the completion percentage: a schedule that front-loads the price puts your money well ahead of the building. And keep the limits in mind. In a cancellation the law requires a refund of what you paid; it does not return your time or underwrite the price. For Davies+Harrison clients, payments, documents and handover progress live in D+H Invest, our private investor platform, so client and adviser see the same picture.
Davies+Harrison is DAH Real Estate Brokerage L.L.C., RERA ORN 53447.
Sources (19)
- 1 Government of Dubai, Law No. (8) of 2007 Concerning Escrow Accounts for Real Estate Development in the Emirate of Dubai, 6 May 2007, https://dlp.dubai.gov.ae/Legislation%20Reference/2007/Law%20No.%20%288%29%20of%202007.html,, retrieved 8 Sep 2026.
- 2 Government of Dubai, Law No. (13) of 2008 Regulating the Interim Property Register in the Emirate of Dubai, 14 Aug 2008, https://dlp.dubai.gov.ae/Legislation%20Reference/2008/Law%20No.%20%2813%29%20of%202008.html,, retrieved 8 Sep 2026.
- 3 Government of Dubai, Executive Council Resolution No. (6) of 2010 Approving the Implementing Bylaw of Law No. (13) of 2008 Regulating the Interim Real Property Register in the Emirate of Dubai, 14 Feb 2010, https://dlp.dubai.gov.ae/Legislation%20Reference/2010/Executive%20Council%20Resolution%20No.%20%286%29%20of%202010%20Approving%20the%20Implementing%20Bylaw%20of%20Law%20No.%20%2813%29%20of%202008.html,, retrieved 8 Sep 2026.
- 4 Government of Dubai, Law No. (19) of 2017 Amending Law No. (13) of 2008 Regulating the Interim Real Property Register in the Emirate of Dubai, 18 Oct 2017, https://dlp.dubai.gov.ae/Legislation%20Reference/2017/Law%20No.%20%2819%29%20of%202017%20Amending%20Law%20No.%20%2813%29%20of%202008%20Regulating%20the%20Interim%20Real%20Property%20Register%20in%20the%20Emirate%20of%20Dubai.html,, retrieved 8 Sep 2026.
- 5 Government of Dubai, Decree No. (33) of 2020 Concerning the Special Tribunal for Unfinished and Cancelled Real Property Projects in the Emirate of Dubai, 24 Nov 2020, https://dlp.dubai.gov.ae/Legislation%20Reference/2020/Decree%20No.%20%2833%29%20of%202020%20Concerning%20the%20Special%20Tribunal.html,, retrieved 8 Sep 2026.
- 6 Dubai Land Department, Register Project, updated 3 Sep 2026, https://dubailand.gov.ae/en/eservices/register-project/,, retrieved 8 Sep 2026.
- 7 Dubai Land Department, Escrow Account activation, updated 3 Sep 2026, https://dubailand.gov.ae/en/eservices/request-to-activate-an-escrow-account/,, retrieved 8 Sep 2026.
- 8 Dubai Land Department, Real Estate Ad Permit, updated 3 Sep 2026, https://dubailand.gov.ae/en/eservices/real-estate-ad-permit/,, retrieved 8 Sep 2026.
- 9 Dubai Land Department, Approved escrow account trustees, updated 3 Sep 2026, https://dubailand.gov.ae/en/eservices/certified-escrow-agents/escrow-account-details/,, retrieved 8 Sep 2026.
- 10 Dubai Land Department, Licensed Developers, updated 3 Sep 2026, https://dubailand.gov.ae/en/eservices/approved-real-estate-developers/,, retrieved 8 Sep 2026.
- 11 Dubai Land Department, Project Status Enquiry, updated 3 Sep 2026, https://dubailand.gov.ae/en/eservices/real-estate-project-status-landing/,, retrieved 8 Sep 2026.
- 12 Dubai Land Department, Dubai REST, updated 3 Sep 2026, https://dubailand.gov.ae/en/eservices/dubai-rest/,, retrieved 8 Sep 2026.
- 13 Dubai Land Department, Licensed Real Estate Brokers, updated 3 Sep 2026, https://dubailand.gov.ae/en/eservices/licensed-real-estate-brokers/,, retrieved 8 Sep 2026.
- 14 Dubai Land Department, Verify License and Permits, updated 3 Sep 2026, https://dubailand.gov.ae/en/eservices/validate-real-estate-licenses-and-permits/,, retrieved 8 Sep 2026.
- 15 Dubai Land Department, Dubai Land Department provides 'Madmoun' service to verify validity of real estate ads via QR codes, 18 Apr 2023, https://dubailand.gov.ae/en/news-media/dubai-land-department-provides-madmoun-service-to-verify-validity-of-real-estate-ads-via-qr-codes/,, retrieved 8 Sep 2026.
- 16 Dubai Land Department, Request to register the initial sale, updated 3 Sep 2026, https://dubailand.gov.ae/en/eservices/request-to-register-the-initial-sale/,, retrieved 8 Sep 2026.
- 17 Bayut, Step-by-step guide to escrow account transfer with DLD, updated 24 Sep 2025, https://www.bayut.com/mybayut/escrow-account-transfer-dld-dubai/,, retrieved 8 Sep 2026.
- 18 Betterhomes, Buying Property in Dubai From Abroad: A Safe Buyer's Guide, 25 Aug 2026, https://www.bhomes.com/en/blog/definitive-guides/buying-property-in-dubai-from-abroad,, retrieved 8 Sep 2026.
- 19 Property Finder, Top 15 Questions to Ask Before Buying an Apartment in Dubai, 2 Sep 2026, https://www.propertyfinder.ae/blog/what-to-ask-when-buying-an-apartment/,, retrieved 8 Sep 2026.
This is general information, not financial, tax or legal advice for your situation.
Next Step
Tell us what you are looking for
Register your interest and a member of our team replies personally, usually the same working day. Confidential, no obligation.
Frequently Asked Questions
An accredited trustee bank holds it in the project's name, and the developer draws on it only under activation terms tied to construction progress (Dubai Land Department, Escrow Account activation, 3 Sep 2026). Five per cent stays back for a year after the units are registered (Government of Dubai, Law 8 of 2007).
Search the project on Project Status Enquiry, compare the Escrow Bank Name and Escrow Account with your contract, and confirm the bank is one of the 29 approved trustees (Dubai Land Department, Project Status Enquiry and Approved escrow account trustees, 3 Sep 2026). If either does not match, do not pay.
Oqood is the entry of an off-plan sale in the interim register; an unregistered sale is void (Government of Dubai, Law 13 of 2008). The developer must register the SPA within 90 days of signing, at 2 per cent from each side plus AED 20 (Dubai Land Department, Request to register the initial sale, 3 Sep 2026).
No. A broker must pay the price into the project escrow account and may not route it through its own account or take commission first (Government of Dubai, Resolution 6 of 2010, Art. 12).
Yes, with RERA's approval. A transfer to another trustee needs a Land Department technical report no older than four months and carries no fee (Bayut, 24 Sep 2025). Ask for the new details in writing.
No. The law protects the funds, not the date. Your remedy for delay is whatever your SPA provides and, if RERA cancels the project, a refund of all payments (Government of Dubai, Law 19 of 2017).
Related Insights
Continue Reading
Can you get a UAE Golden Visa by buying property in Dubai?
Yes. Property with a purchase value of AED 2 million or more, off-plan or mortgaged included, qualifies you for a renewable ten-year residence permit.
Freehold or leasehold in Dubai: what do you actually own?
Freehold registers you as owner of the unit and its share of the land with no time limit; leasehold and usufruct are registered rights for up to 99 years.
Who pays a Dubai property adviser, and what does independent mean?
By law the party who appoints a broker pays. By custom resale buyers pay about 2 per cent, off-plan buyers nothing. Independence is conduct, not a licence.